What the buyer needs
AI summaryThe government authority in Macon, Georgia, requires construction manager at risk services for a stormwater pump installation at the Walker Road Landfill. The project includes constructing and installing a new stormwater pump system.
Services include preconstruction activities such as design collaboration, constructability reviews, value engineering, and cost estimating. The contractor will also develop a master schedule and solicit bids for trades.
During construction, the contractor will manage subcontracts, site safety, and the installation of permanent power infrastructure. They will ensure equipment is mounted and aligned, and then decommission and remove the existing pumps.
Scope of work
- Preconstruction collaboration with Hofstadter and Associates, constructability reviews, value engineering, and life-cycle cost analysis
- Master schedule development, milestone updates, and cost estimates at 30%, 60%, and 90% design
- Competitive pricing solicitation targeting at least three qualified bids per trade/supplier above $5,000
- Guaranteed Maximum Price (GMP) proposal submission based on finalized construction documents
- Management of all subcontracts, purchase orders, and site safety during construction
- Installation of permanent power infrastructure for the new electric-driven stormwater pump
- Delivery, mounting, and alignment of Godwin Dri-Prime Model CD150M pump set or approved equal
- Safe decommissioning and removal of existing diesel-driven pumps at the entrance road
How proposals are evaluated
| Criterion | Weight / scoring |
|---|---|
| Firm Experience & Past Performance (Similar municipal projects) | 25 Points |
| Qualifications of the Proposed Team (Preconstruction and Construction roles) | 25 Points |
| Project Approach & Methodology (Constructability, scheduling, electrical coordination) | 15 Points |
| Current Workload & Availability (Capacity to successfully execute the project timeline) | 15 Points |
| Pricing Proposal (Preconstruction Fee, CM Fee %, and General Conditions evaluated against a $300,000 placeholder budget) | 20 Points |
Minimum qualifications
- Licensed General Contractor in the State of Georgia
- Demonstrate ability, capacity, and financial backing to perform required work
- Similar experience in municipal water infrastructure, electrical utility routing, or pump station projects
- Able to provide a 100% Performance and Payment Bond upon GMP acceptance
Documents to include with your response
- Letter of Interest identifying firm, primary contact, and acknowledgment of addenda
- Firm Experience & Track Record with at least three municipal water/wastewater project references
- Project Team resumes for Project Executive, Preconstruction Manager, and Site Superintendent
- Approach to Preconstruction & CMAR
- Current Workload & Financial Capacity summary and surety letter confirming bonding capacity
- Pricing Proposal (submitted separately) with Preconstruction Fee, CM Fee %, and General Conditions
How to submit
- Method
- Hard copy and electronic copy
- Instructions
- Submit one (1) original and three (3) hard copies of the proposal, alongside one (1) electronic copy; Pricing Proposal submitted separately