What the buyer needs
AI summaryThe Gwinnett County Board of Commissioners requests sealed bids for the construction of the Beaver Ruin Diversion Pump System Grinders Replacements project. The scope includes replacing three grinder units and nine slide gates, raising concrete wet well baffle wall and platform elevations, relocating the flushing system, and installing electrical conduit with MCC configuration. Firms on the Gwinnett County ineligible source list or those debarred or suspended may not submit bids. The contractor must achieve substantial completion within 450 days of contract commencement and final completion within 30 days thereafter. A non-mandatory pre-bid conference requiring personal protective equipment takes place onsite on October 14, 2026, at 10:00 AM local time, and questions are due to Anna West by October 23, 2026, at 3:00 PM local time. Bidders must purchase documents from Ardurra Group Inc. for $250 and deliver sealed bids by November 20, 2026, at 2:50 PM local time for a virtual bid opening.