What the buyer needs
AI summaryThe South Georgia Governmental Services Authority, d/b/a CNSNext, requests proposals for the construction of fiber to the home outside plant in the Thomasville service area. The work will be performed under a unit-price construction agreement, with no federal funds involved.
The contractor shall perform all labor, supervision, equipment, materials, testing, and services as required by the contract documents. This includes complying with applicable law, industry standards, safety regulations, and environmental requirements.
Substantial completion is required within 90 calendar days and final completion within 150 calendar days after the notice to proceed. Liquidated damages of $500.00 per calendar day will be assessed for failure to achieve final completion within the contract time.
Before the notice to proceed, the contractor must provide a performance bond and a payment bond, each for 100 percent of the contract amount. Contractor shall maintain specific insurance coverages until final completion.