What the buyer needs
AI summaryParks Canada requires a contractor to dismantle the northwest bastion structure at Fort Langley National Historic Site and purchase new timbers. The contractor is responsible only for dismantling and purchasing new timbers; reassembly is not included. Bids must be submitted via fax or email to a specific address and facsimile number. The maximum email file size is 15 megabytes, and bids with links will not be accepted. The work must be completed by March 31, 2027. An optional site visit is scheduled for November 18, 2026, with attendance confirmation required by November 17, 2026. The selection process includes criteria for providing socioeconomic benefits to Indigenous communities. The contractor must ensure agreed-upon benefits for Indigenous People and Businesses.