What the buyer needs
AI summaryEtowah Water & Sewer Authority invites contractors to submit pre-qualification applications for the expansion of the existing Dawson Forest WRF to 2.5 MGD in Dawsonville, Georgia. The project requires furnishing all materials, equipment, and labor for mechanical bar screen installation, SBR tank upgrades and construction, post EQ pump, disc filter and UV equipment, aerobic digester work, and civil, electrical, and instrumentation improvements. Eligible applicants must hold a Georgia Utility Contractor's license, maintain sufficient bonding capacity for an assumed $20,000,000 construction cost, and demonstrate experience on projects of at least $15,000,000.00 completed after January 1, 2016. Contractors must submit completed PDF packages via email to Tim Collins at [email protected] by 5:00 p.m. local time on December 18, 2026, without submitting hard copies. The Authority will evaluate technical and corporate experience and notify applicants of their pre-qualification status on or before January 8, 2027. No bid will be opened unless the Authority has approved the bidder.
Scope of work
- Installation of Mechanical Bar Screen No. 2 at Influent Pump Station
- Miscellaneous upgrades to existing SBR Tanks No. 1 and No. 2
- Construction of SBR Tanks No. 3 and No. 4 and appurtenances
- Installation of Post EQ Pump No. 3
- Installation of additional Disc Filter Equipment and UV Equipment
- Miscellaneous upgrades to existing Aerobic Digesters No. 1 and No. 2
- Conversion of two abandoned SRB tanks to Aerobic Digesters No. 3 and No. 4
- Miscellaneous civil, electrical, instrumentation, and blower building improvements
Minimum qualifications
- Operated under current corporate name for the last five years
- Licensed Georgia Utility Contractor
- Two municipal wastewater treatment plant upgrade/expansion projects with NPDES stream discharge permit
- Each qualifying project must have a construction contract amount of at least $15,000,000.00
- Each qualifying project must have been completed after January 1, 2016
- At least 50 percent of labor-related items performed by own work force
- Project management and technical staff with at least two years of relevant experience
- Joint Ventures will not be approved for this project
Documents to include with your response
- Completed Application for Bidder's Pre-Qualification
- Technical experience details for two qualifying projects
- Corporate headquarters, regional offices, and officers biographical summary
- Statement of bonding capacity, bonding company, and insurance agent contacts
- List of major equipment proposed (owned or leased)
- Statements on project completion, liquidated damages, claims, and litigation history
- Experience of proposed on-site project manager and/or field superintendent
- List of all other projects currently under contract
- Photocopy of Applicant's Georgia Utility Contractor's license
How to submit
- Method
- Electronic via email in PDF format
- Instructions
- Submit in PDF format via email using subject line 'PRE-QUALIFICATION APPLICATION – DAWSON FOREST WRF EXP. TO 2.5 MGD'. Do not submit hard copies.