AI summaryThe project involves constructing a wetland to treat water from an existing drainage district tile and ditch using a solar panel powered pump. Work includes selective clearing, excavation, grading, and installing inlet and outlet concrete structures, a solar-powered pump system, pipe, riprap, and seeding.
Key quantities include approximately 13,900 cubic yards of earthwork, 1,875 linear feet of pipe, 20 tons of riprap, and 27.3 acres of seeding. The estimated construction cost range for this project is $175,000 to $275,000.
Construction is anticipated to be completed by November 1, 2027, with seeding by December 15, 2027. Seeding must adhere to specified periods, with potential companion crops and weed control measures as needed.
The solicitation requires mobilization and demobilization of contractor forces and equipment. Access areas will be restored, as close as practical, to their original condition, and any removed fencing replaced with similar materials.