What the buyer needs
AI summaryCherokee County Water & Sewerage Authority seeks bids for water main relocation. The project includes 11,360 LF of 36" DIP Water Main, 1,400 LF of 20" DIP Water Main, 15,500 LF of 12" DIP Water Main, and 20,200 LF of 8" DIP Water Main.
Bids are due by December 17, 2026, at 10:00 A.M. local time. Substantial completion is required within 960 calendar days, with final completion not exceeding 1,640 consecutive calendar days.
Contractors must submit a Contractor Qualification Statement and Questionnaire. Subcontractors performing over 20 percent of the work must also meet minimum qualifications.
Questions regarding the bid must be submitted via email by December 9, 2026, at 3:00 P.M. to Robert Bartlett at AtkinsRealis USA.