AI summaryThis project is for a Breakpoint nutrient reduction wetland. The work involves selective clearing, excavation, grading, and installation of various structures and materials.
Scope of work
- Site preparation, selective clearing, excavation, and grading (18,151 cubic yards of earthwork)
- Steel sheetpile installation (1,150 square feet)
- Tile and pipe installation (1,268 linear feet)
- CMP water control structure and CMP inlet riser
- Stoplog storage structure
- Loose rock riprap (668 tons) with concrete grout (72 cubic yards)
- Turf reinforcement mat Type 5B (430 square yards) and silt fence (515 LF)
- Seeding and mulching for protective cover (5 acres)